Pre Commissioning Activities 36" Israel dn36"


Client

H.Z. Hershkovitz Metal and Electrical Works Ltd.

Contractor

---

Location

Israel

Time

June 2021

CTE PIACENZA - Pipeline Cremona-Piacenza

Nitrogen Inertisation, cleaning, Gas Free certification (43km dn10" line)
Length: 43000 meters

Client

A2A S.p.A.

Contractor

---

Location

Cremona-Piacenza, Italy

Time

March 2021

Interconnection TAP-SNAM Rete Gas

Cleaning, Caliper Inspection, Drying dn56"
Length: 8000 meters

Client

Max Streicher S.p.A.

Contractor

---

Location

Melendugno (LE), Italy

Time

July 2020

Pipeline DN 400 (16") Centrale "Federico II" Brindisi Nord-Brindisi Sud

Cleaning, Gauging, Deformation, Inertial Mapping Service and Magnetic Flux Leakage Inspection (MFL)
Length: 11500 meters

Client

Enel Produzione S.p.A.

Contractor

Enel Produzione S.p.A.

Location

Italy

Time

August 2016

Pipeline DN 1400 (56") Zimella-Cervignano, DP 75 bar

Step 1

Client

S.A.L.P. S.p.A. - I.CO.P. S.p.A.

Contractor

SNAM Rete Gas S.p.A.

Location

Italy

Time

May 2015

Gas pipeline DN 1400 (56") Zimella-Cervignano, DP 75 bar

Step 9, 10 & 11

Client

Bonatti S.p.A.

Contractor

SNAM Rete Gas S.p.A.

Location

Italy

Time

October 2014

Pipeline DN 400 (16") Gonars-Torviscosa


Client

Edison Energia S.p.A.

Contractor

---

Location

Italy

Time

August 2014

Natural gas pipeline BOTAŞ construction project Sakarya-Karasu


Client

Hitaş İnş. ve Tic. Ltd. Şti.

Contractor

BOTAŞ - Petroleum Pipeline Corporation

Location

Turkey

Time

October-November 2013

Gas pipeline DN 12" Larino-Chieuti

Step 1 & 2
Length: 46357 meters

Client

Romana Costruzioni S.p.A.

Contractor

SGI S.p.A.

Location

Italy

Time

November 2012